A PROJECT MANAGER IS REVIEWING THE RISKS OF HER PROJECT. ONE OF THE...

9. A project manager is reviewing the risks of her project. One of the risksshe is reviewing has an impact of $25,000 and an associated probabilityof 10%. The risk is associated with an activity that is the predecessor toseven other activities in the schedule. All eight activities are on the criti-cal path. The seven other activities have a budget of $75,000. What isthe expected value of this risk?a. $10,000b. $100,000c. $25,000d. $2,500