29. A project manager is managing a project and is considering the resched-
ule of an activity because one of the project engineers must work on
this activity and another activity at the same time. Each of the activities
is scheduled to have a duration of two weeks. One of the activities is on
the critical path and the other activity has eighteen days of free float.
The project manager should:
a. Reschedule the activity that has no float.
b. Reschedule the activity with float.
c. Ask the engineer to work overtime.
d. Reschedule both activities to take advantage of the float on each.