30. A project manager is managing a project that has reached the end of theplanning phase. The work scope has been agreed to and definitive costestimates have been completed for the project. The total estimated costof the project is $100,000. It is reasonable to expect that the projectwill not cost over which of the following values?a. $100,000b. $110,000c. $125,000d. $175,000