A PROJECT MANAGER IS MANAGING A PROJECT DURING THE PLANNING PHASE....

34. A project manager is managing a project during the planning phase.She chooses to use a precedence network diagram as a graphic planningtool to assist in making the project schedule. The most important reasonfor using the network diagram as a graphic planning tool is that it makesit easier to see which aspect of the project plan better than the othertools available?a. The probability that the tasks will be completed on timeb. The logical relationships between activities in the schedulec. The start and finish dates of the activitiesd. The float between activities