30. A project manager looks at her schedule and sees that there has been a

delay in completing a task. It seems practical to move a person from

another task that is an expert on the work that is behind. There is a

choice of using two different persons that are working on two different

tasks. One person is working on a task that has five days of free float

and the other is working on a task that has eight days of total float and

no free float. Which person should be used to help out?

a. The person working on the task with free float of five days.

b. The person working on the task with total float of eight days.

252 Preparing for the Project Management Professional Certification Exam

c. Either person can be used.

d. A person should be brought in from outside the project.