39. In distinguishing PERT from CPM one could say that:
a. PERT is probabilistic and CPM is deterministic.
b. CPM is probabilistic and PERT is deterministic.
c. Either one is deterministic or probabilistic depending on how they
are used.
d. Neither one is deterministic or probabilistic.