35. A project manager is approached by the major stakeholder in the project
and is asked to reduce the time for the scheduled completion of the
project. The project manager reviews the project plans and the progress
that has been made on the project. He or she decides that the best
approach to solving this problem is to fast track the project until the
new project completion date can be achieved. Which of the following
will be done by the project manager?
a. Reduce the project schedule by any means that are possible
b. Reduce the project schedule by applying any practical means neces-
sary
c. Reschedule activities that would be done in sequence to activities
that can be done in parallel
d. Inform the stakeholder that this will change the project schedule
and will require additional funds to comply with the request