QUESTIONS 12 THROUGH 15 REFER TO THE DIAGRAM IN FIGURE 2 AND THE TABLE...

35. A project manager is approached by the major stakeholder in the project

and is asked to reduce the time for the scheduled completion of the

project. The project manager reviews the project plans and the progress

that has been made on the project. He or she decides that the best

approach to solving this problem is to fast track the project until the

new project completion date can be achieved. Which of the following

will be done by the project manager?

a. Reduce the project schedule by any means that are possible

b. Reduce the project schedule by applying any practical means neces-

sary

c. Reschedule activities that would be done in sequence to activities

that can be done in parallel

d. Inform the stakeholder that this will change the project schedule

and will require additional funds to comply with the request