A PROJECT MANAGER IS DOING RISK ANALYSIS WITH THE PROJECT TEAM MEM...

40. A project manager is doing risk analysis with the project team members.They are concerned about evaluating the risks in such a way that therisks will be ranked according to their severity in relation to the project.What method should be used to rank the risks in the order of impor-tance?a. Determine the expected valueb. Determine the cost of the impactc. Determine the probabilityd. Use subjective analysis