A PROJECT MANAGER DISCOVERS THAT THERE IS A PART OF THE PROJECT THA...

1. A project manager discovers that there is a part of the project that con-tains some risk. His strategy with this risk is to subcontract the work toan outside supplier by using a firm fixed price contract. Which of thefollowing must the project manager do?a. The project manager should make certain that the project team doesnot reveal the risk to the supplier until the contract is signed.b. The project manager should make every effort to make sure that thesupplier is made aware of the risk after the contract is signed.c. The project manager should make sure that the supplier understandsthe risk before the contract is signed.d. The project manager should assign a member of the project team tomonitor the activity of the supplier to make sure that the supplierdeals with the risk properly if it occurs.