20. A project manager purchases 3,500 widgets for his project. The widgets
are delivered on time, but there are many defects in the paint that is on
302 Preparing for the Project Management Professional Certification Exam
the surface of the widgets. The project manager returns the parts to the
vendor for repair and rework. The vendor complains that the paint job
quality was not specified in the contract and it is not his responsibility
to repair the parts. It is likely that the parts will be repaired by the
vendor because of:
a. Expressed warranty.
b. Implied warranty.
c. Past business practices.
d. Threat of legal action by the project team.