9. During a project meeting a disagreement between two members of the
project team began. The disagreement was over a technical detail of the
project. The project manager was in attendance in the meeting. It is
important that the conflicting opinions of the two team members be
resolved as quickly as possible. It is even more important that the differ-
ence of opinion be resolved correctly. What should the project manager
do?
a. The project manager should make the decision right away to save
time and not let the two disagreeing parties stay in disagreement
very long.
b. End the meeting and give everyone a few days to cool off.
c. Assign someone to find out more factual information about the
problem.
d. The project manager should suggest a compromise between the two
disagreeing team members.