30. A project manager hears a rumor through the project team that the
client for the project is supposed to visit the project team office and
present the project manager with a purchase order for a large change in
the project. The change will authorize new budget for $50,000. This is
an example of what type of communications?
312 Preparing for the Project Management Professional Certification Exam
a. Formal
b. Informal
c. Verbal
d. Nonwritten