IN A VERY LARGE PROJECT HAVING A BUDGET OF $5 MILLION AND A PROJEC...

29. In a very large project having a budget of $5 million and a project teamof over one hundred persons, the project manager constructs a workbreakdown structure. The project manager will do the WBS to thedetail level of which of the following?a. Taskb. Activityc. WBS elementd. Work package