A PERSON WHO IS INVOLVED IN OR MAY BE AFFECTED BY THE ACTIVITIES OR...

3. A person who is involved in or may be affected by the activities oranyone who has something to gain or lose by the activity of the projectis called a:a. Team member.b. Customer.c. Stakeholder.d. Supporter.The following should be used for questions 4 through 6.A project manager is assigned to a project early in the project life cycle. Oneof the things that must be done is to do a justification for the project. Sincevery little information is known about the project, the estimates are consid-ered to be rough estimates. The following table is the project manager’sestimate of the cash flows that will take place over the next five years.

235

End of Year Cash Flow In Cash Flow Out1 0 500,0002 300,000 90,0003 400,000 100,0004 100,000 175,0005 50,000 35,000