21. A project is coming to a close, and the project manager is listing the
things that must be done to close out the project. One of the things
that must be done by the person responsible for contract administration
is:
a. Issue letters of recommendation for the project team.
b. Issue a formal written notice of project completion to the contrac-
tors.
c. Put a legal notice in the newspapers indicating that all invoices must
be submitted.
d. Request final inspection reports for all vendor supplied materials.