A PROJECT MANAGER IS REVIEWING THE WORK BREAKDOWN STRUCTURE FOR HE...

18. A project manager is reviewing the work breakdown structure for herproject. The WBS for the project represents:a. All the tangible items that must be delivered to the client.b. All the work that must be completed for the project.c. The work that must be performed by the project team.d. All the activities of the project.