27. A project manager is managing a project to design a software system
for a client. She decides to subcontract the work to a programming
subcontractor. The subcontractor fails to deliver the work on time, and
the project manager invokes a penalty clause that was written into the
contract. It is found that the person signing the contract was under
twenty-one years of age (the legal age where the contract was signed).
What can be done?
a. The company can invoke the penalty clause, and it must be hon-
ored.
b. The work must be completed by the subcontractor, and the penalty
clauses must be deducted from the amount paid to the subcon-
tractor.
c. The company should renegotiate the contract.
d. The contract is void for lack of competent parties, and no additional
work should be done.