BTHE WORK BREAKDOWN STRUCTURE REPRESENTS ALL THE WORK THAT MUST BE DON...

18. Answer: b

The work breakdown structure represents all the work that must be done in

order to complete the project. Doing all the work will deliver all the tangible

results to the client. In most projects there will also be deliverables that will be

delivered to other stakeholders. Work that is done by contractors and those not

on the project team is included in the WBS. The lowest level of the WBS is

the work package (according to PMI). Work packages can be broken down into

tasks, and tasks can be broken down into activities.