ATHE CHART OF ACCOUNTS IS THE SYSTEM USED TO MONITOR PROJECT COSTS AS...
TÀI LIỆU PROJECT MANAGEMENT PROFESSIONAL-CHAPTER 11B (ANSWER KEY) DOC
Nội dung
Đáp án tham khảo
2. Answer: a
The chart of accounts is the system used to monitor project costs as defined by
PMI.