ENDING 31 JULY.A PERT CHART SHOWS DEPENDENCIES, FOR EXAMPLE, THAT A...

3. ending 31 July.A Pert chart shows dependencies, for example, that architectural design must becompleted before detailed design. Parallel activities, such as designing two componentsat the same time, can also be shown. A Pert chart like this allows the critical path to beidentified easily. This is the path through the chart that determines the overall durationof the project.During the course of the development, progress of the project is monitored andcompared with the Pert diagram. Should any stage take longer or shorter than planned,the diagram is updated to reflect the new situation.