BTHE PRECEDENCE NETWORK DIAGRAMMING TOOL IS USED BECAUSE IT BEST SHOWS...
34. Answer: b
The precedence network diagramming tool is used because it best shows the
logical relationships between the activities in the schedule. The Gantt chart
shows the project schedule graphically indicating the start and finish for each
activity. The milestone chart shows the start or completion for specific groups
of activities on a summarized chart.