A PROJECT MANAGER IS LOOKING AT THE RISK ASSOCIATED WITH THE PROJE...

11. A project manager is looking at the risk associated with the projectschedule. Realizing that if the risks occur the project will be deliveredto the stakeholders late, the project manager decides to consider the riskand promise delivery later than the most likely project completion date.He then takes the time between the promise date and the most likelycompletion date and distributes it among the activities of the projectschedule. This creates float in the schedule. This process is called:a. Schedule delay.b. Critical chain scheduling.c. Buffering.d. Contingency scheduling.