THE PROJECT MANAGER HAS CRITICAL PARTS THAT ARE NEEDED FOR THE PRO...

27. The project manager has critical parts that are needed for the project. Ifthe first order of parts is delivered late, the project will be late delivering

... 9618$$

CH15

09-06-02 15:00:35

PS

Team-Fly

®

a critical deliverable to the customer. The seller that has been selectedto make these parts for the project has been used in the past and histori-cally has failed to deliver on time 10% of the time. Another vendor canbe found that has the same delivery record. The project manager decidesto divide the order between the two vendors in hopes that at least oneof them will deliver on time. What is the probability that at least oneof the vendors will deliver on time?a. .81b. 1.8c. .99d. 1.0