39. A project manager must make a decision about a risk in his project. Heexamines the extent to which the uncertainty of each of the elements ofthe project affects the objective being examined when all other uncer-tain elements are held at their baseline values. This technique is calledwhich of the following?

286

Preparing for the Project Management Professional Certification Exam

a. Decision tree analysisb. Expected value analysisc. Sensitivity analysisd. Simulation