YOU ARE THE PROJECT MANAGER FOR A LARGE PROJECT THAT IS COMPLETED...
10. You are the project manager for a large project that is completed on
time and on budget. The customer and all of the stakeholders are
pleased with the results. As a direct result of the successful completion
of the project, your manager approves a bonus of $25,000 to you. There
are fifteen members of the project team. One of the people on the
project team has been a very low contributor to the project; the other
fourteen have all been above standard. What should you do with the
money?
a. Keep the money yourself; you deserve it, and the manager gave it to
you.
b. Divide the money equally among all the team members.
c. Ask the team members how they would divide the money.
d. Divide the money equally among the team members except for the
substandard team member.