YOU ARE THE PROJECT MANAGER FOR A LARGE PROJECT THAT IS COMPLETED...

10. You are the project manager for a large project that is completed on

time and on budget. The customer and all of the stakeholders are

pleased with the results. As a direct result of the successful completion

of the project, your manager approves a bonus of $25,000 to you. There

are fifteen members of the project team. One of the people on the

project team has been a very low contributor to the project; the other

fourteen have all been above standard. What should you do with the

money?

a. Keep the money yourself; you deserve it, and the manager gave it to

you.

b. Divide the money equally among all the team members.

c. Ask the team members how they would divide the money.

d. Divide the money equally among the team members except for the

substandard team member.