THE EFFECT OF RISK ON SCHEDULE DATES FOR THE PROJECT CREATES AN ARR...

8. The effect of risk on schedule dates for the project creates an array ofdates that are possible for project completion. In a typical project themost likely date for the project will have which of the following relation-ships with the expected value for the project completion date?a. The most likely date will be earlier than the expected value date.b. The most likely date will be later than the expected value date.c. Both dates will have the same likelihood.d. The most likely date and the expected value date will occur at thesame time.