CIN ORDER FOR THE PROJECT TO HAVE A 5% PROBABILITY OF BEING LATE, THER...

26. Answer: c

In order for the project to have a 5% probability of being late, there is a 95%

... 9618$$

CH20

09-06-02 15:00:59

PS

Team-Fly

®

323

Scope Management

probability that the project will be delivered on time or earlier. In terms of the

PERT calculation this means that 2 standard deviations should be added to the

expected value date of May 30. Since there is a one month difference between

the 95% promise date of June 30 and the expected value of May 30, the stan-

dard deviation must be one-half month. This is a better answer than fifteen

days because on the basis of a five-day work week this is close to three weeks.