26. Answer: c
In order for the project to have a 5% probability of being late, there is a 95%
... 9618$$
CH20
09-06-02 15:00:59
PS
Team-Fly
®323
Scope Management
probability that the project will be delivered on time or earlier. In terms of the
PERT calculation this means that 2 standard deviations should be added to the
expected value date of May 30. Since there is a one month difference between
the 95% promise date of June 30 and the expected value of May 30, the stan-
dard deviation must be one-half month. This is a better answer than fifteen
days because on the basis of a five-day work week this is close to three weeks.