The client should pay, because the signing of the WBS constituted an agree-

ment between the company managing the project and the client. Work that is

not specified in the WBS is not part of the project scope. In reality this is

sometimes not the case. Companies will frequently do work that is outside of

the project scope as defined by the WBS in order to ensure the goodwill of the

client.