A NEW PROJECT HAS BEGUN. THE PROJECT CHARTER HAS BEEN WRITTEN AND...

20. A new project has begun. The project charter has been written and theproject manager has been assigned. The project manager is preparingthe work breakdown structure for the project. The WBS is typicallyused for:a. Explaining the scope of the project relevant to the client.b. The basis for organizing and defining the total scope of the project.c. Showing the resource conflicts that exist in the project.d. The logical relationship between tasks in the project.