THE PROJECT TEAM HAS PUT TOGETHER A PROJECT PLAN FOR A PROJECT, AN...

21. The project team has put together a project plan for a project, and theplan has been approved by the stakeholders. The customer asks theproject manager if the project can be delivered seven weeks sooner. Thecustomer offers sufficient monetary incentive for the project manager.The project manager decides to fast track the project. This decision will:a. Increase risk.b. Decrease risk.c. Not affect risk.d. Risk change cannot be determined.