A PROJECT MANAGER IS PREPARING THE BUDGET FOR THE PROJECT. THERE A...

29. A project manager is preparing the budget for the project. There areseveral inputs to the budgeting process that the project manager willuse. One of the things that the project manager will not use is the:a. Cost estimates.b. Project schedule.c. Cost baseline.d. Work breakdown structure.

TE AM FL Y

Use the following information for questions 30 and 31.A project team has a programmer on the team. The programmer will workon the project for twenty-six weeks as a full time team member. Her utiliza-tion is 72%, productivity is 80%, basic wages are $50 per hour, fringe bene-fits are 30%, and overhead costs are 50% of wages plus fringe benefits. Usea forty hour work week.