THE CONTINGENCY BUDGET WILL

32. The contingency budget will:a. Reduce the probability of scope changes.b. Reduce the probability of cost overruns.c. Increase the probability of a cost overrun.d. Increase the probability of scope changes.The following table should be used for questions 33, 34, and 35.A project manager is assigned to a project early in the project life cycle. Oneof the things that must be done is to do a justification for the project. Sincevery little information is known about the project, the estimate is consideredto be rough estimates. The following table is the manager’s estimate of thecash flows that will take place over the next five years.End of Year Cash Flow In Cash Flow Out1 0 500,0002 300,000 90,0003 400,000 100,0004 100,000 175,0005 50,000 35,000