A PROJECT IS BEING MANAGED BY A PROJECT MANAGER. A LARGE PORTION O...

23. A project is being managed by a project manager. A large portion of the

work of the project is being subcontracted to an outside vendor. During

the project it is found that a significant change in the design of the

project is necessary. The project manager should:

a. Issue a change notice to the contractor immediately.

b. Issue a purchase order to investigate the change.

... 9618$$

CH17

09-06-02 15:00:42

PS

c. Notify the contractor of the design change possibility.

d. Rebid the contract.