A LARGE PROJECT IS APPROXIMATELY 50% COMPLETE. THE PROJECT MANAGER...

39. A large project is approximately 50% complete. The project manager

wants to establish some sort of reward system for the project team mem-

bers. The project manager hopes that the reward system will help the

team morale. Which of the following characteristics for reward systems

should the project manager pay the closest attention to?

a. The reward must be a significant monetary value.

b. The reward should be distributed to as many team members as pos-

sible.

c. The relationship between the reward and performance must be ex-

plicit.

d. The budget for the reward must come from outside the project

funds.