A PROJECT MANAGER WORKING ON A LARGE PROJECT FINDS THAT THERE ARE...

37. A project manager working on a large project finds that there are severalrisks that have a severity that is higher than the acceptable risk tolerance.They cannot be avoided or deflected. The project manager will need touse which of the following approaches?a. Change the risk tolerance of the clientb. Buy insurance for the riskc. Ignore the riskd. Mitigate the risk