32. A project manager is dealing with risk analysis on a software develop-ment project. There is a risk that the module that creates the mostimportant report that the system will create will not work properly andwill require 200 person-hours to correct. The project manager decidesto do nothing about this risk. Which of the following risk strategies isthe project manager employing?a. Acceptanceb. Avoidancec. Mitigationd. Deflection