6.3 RISK ALLOCATION A PROPERLY WRITTEN CONSTRUCTION CONTRACT WILL AL...
A properly written construction contract will allocate the risk of loss or dam-
age occurring to the project clearly and completely, so that each party knows
precisely which risks he bears and what the consequences are should a risk
eventuate.
When two or more parties engage in a construction project, there are many
different kinds of risk of which each will need to be aware. These include the
following:
●
There are design-related risks. Does the design for critical parts of the plant
or structure, for example, achieve the performance expected? Is it efficient
and workable?
●
There are risks associated with s ite investigations : geotechnical investiga-
tions, for example, where tunnelling or extensive excavation work is required.
●
There are risks associated with the
construction process : the availability of
resources and materials, on time, in the right quantities and of the right
quality; encountering unexpectedly poor ground conditions even where
adequate site investigations have been carried out; the occurrence of
unforeseeable events such as bad weather, flooding, and the risk of injury
to persons and damage to property; and industrial and political risks, of
labour disputes, war, or other civil disturbance.
●
There are
financial risks. Will the employer or owner or developer pay
when the work-stages are achieved? What happens if the contractor
becomes insolvent before the work is completed?
Only if risk is clearly and completely allocated will each party be able to
manage risk efficiently, taking steps to protect against the consequences
9
See pp. 74–75 for a fuller account of the claims procedure under the FIDIC forms.
10
See clause 2.5, but here again the employer is required to notify a claim (such as for an
extension of a contractual defects notification period) at an earlier stage. The contractor is
then in a better position to investigate the claim.
should the risk eventuate. Risk allocation is therefore an essential element
of the efficient management of the project itself.