3 (H). ADDITIONAL TIME AND PAYMENT RISK UNDER CL 3
17.3 (h). Additional time and payment
Risk under cl 17.3: no
extension of time or
(but not profit) if the event was
additional payment unless
Unforeseeable (in the above sense)
specifically provided for.
or was one against which an
experienced contractor could not
reasonably have been expected to
have taken adequate precautions.
Yes (cl 4.1)
Yes (cl 4.1)
Design Responsibility: Must the
design, execute and complete
the works in accordance with
the contract so that when
completed the works will be
fit for the purposes for which
they were intended as defined
in the Contract?
Additional time and payment (plus
Errors in Employer’s
No additional time or
reasonable profit) if the error was
payment for unless an
Requirements
exception within cl 5.1
such that an experienced contractor
(a)–(d) applies
exercising due care would have
discovered the error when
scrutinising the ER (cl 1.9).
12
We have included in this table how the two Books deal with a related head of risk,
‘
Operations of the forces of Nature ’. These are defined in clause 17 of the Yellow Book as ‘
any
operation of the forces of nature which is Unforeseeable or against which an experienced contrac-
tor could not reasonably have been expected to have taken adequate preventative precautions ’ .
3 Types of Construction Contract
We have been looking so far at the different ways in which risk is allocated in
traditional and in turnkey projects and contrasting in particular the ‘balanced’
approach to risk in the FIDIC Red and Yellow Books with the ‘one-sided’ risk
profile of the Silver Book. We suggested that these different risk allocations
are a consequence of the very different dynamics applying to turnkey-type
projects, in which the financial pressures involved operate to make achieving
performance on time and to budget paramount.