19.5 RELEASE FROM PERFORMANCE UNDER THE LAW

4.19.5 Release from performance under the law: Clause 19.7

This provision is intended to enable the parties to be discharged from further

performance if any event or circumstance beyond their control (including,

but not limited to, force majeure) arises:

which makes it impossible or unlawful for either or both of them to fulfil

their obligations; or

which, under the governing law of the contract, entitles them to be released

from further performance.

In either case, a party may give notice to the other of the relevant event or

circumstance. Upon that notice:

the parties will be discharged from further performance (but without pre-

judice to, or not affecting, the rights of either party in relation to previous

breaches of contract, if any); and

the sum payable to the Contractor will be the same as for a termination

under clause 19.6 (see above).

Thus, the parties may be discharged from further performance where

events or circumstances beyond their control prevent them from performing

their obligations in a potentially wider set of situations than force majeure as

defined in the Books. The parties may be excused in any such situation where

under the governing law of the contract they would be entitled to be

discharged.