8.3 DELAYS AND EXTENSIONS OF TIME

4.8.3 Delays and extensions of time: Clause 8.4

We have already considered this topic in Part I (Section 1.7) but it is probably

helpful to summarise here the main points of similarity and contrast between

the two Books.

If any of the circumstances listed under clause 8.4 of the Books occurs and

results in delay to completion of the works, the Contractor is entitled to an

extension of the time for completion subject to giving notice of claim under

clause 20.1.

In the Yellow Book the relevant delay events are:

a variation or other substantial change in the quantity of an item of work;

a cause of delay giving rise to an entitlement under another sub-clause;

exceptionally adverse climatic conditions;

unforeseeable shortages of personnel or goods caused by epidemic or gov-

ernmental actions;

any delay, impediment or prevention caused by or attributable to the

Employer, the Employer ’ s personnel or the Employer ’ s other contractors

on the site.

In the Silver Book, as we saw, only the first, second and last of these grounds

apply (variations, express mention in another clause of the contract or delays

attributable to the Employer).

Moreover, in the Silver Book general conditions, no additional time is per-

mitted for (a) unforeseeable physical conditions (whereas it is under clause