3 WE LOOKED AT THE PROGRAMME AND ITS IMPORTANCE IN PART I (SECTION 1
We looked at the programme and its importance in Part I (Section 1.7).
7
In the Yellow Book the contract comes into effect when the Contractor receives the Letter
of Acceptance and in the Silver after both parties have signed the Contract Agreement.
8
Sometimes the overall work is divided into ‘sections’ of work, each section having its own
commencement and completion dates and other contract stages, although coming under the
same contract as other parts or sections. If the works are to be divided into sections in this way
then this must be provided for in the Particular Conditions (if Silver Book) or Appendix to
Tender (if Yellow) by specifying the part or parts of the works which are to be treated as sections.
The Contractor must submit to the Engineer or Employer his programme
within 28 days after the commencement date (if Silver Book) or 28 days after
notice of the commencement date (if Yellow).
As we saw in Section 1.7, the programme:
●
provides the basis for monitoring the Contractor ’ s progress and planning
Employer/Engineer activities and obligations;
●
becomes a base reference for the Engineer ’ s or Employer ’ s determination
of Contractor ’ s claims for extensions of time for completion arising from
alleged disruption or delay.
The programme must show:
●
the order of execution of the works, including the anticipated timing of
each major stage of the works; in the Yellow Book more details of this are
required (clause 8.3(a));
●
sequencing of the works, taking into account the lead time for obtaining
any approvals;
●
the periods for review of Contractor ’ s Documents; in the Yellow Book
additionally the periods for review of any other submissions, approvals, or
consents mentioned in the Employer ’ s Requirements;
●
the sequence and timing of inspections and tests.
The programme should be accompanied by a supporting report (or method
statement) setting out how the Contractor intends to execute the works and
the resources he intends to use.
If the Engineer or Employer thinks the programme does not comply with
the contract then he must give notice to the Contractor within 21 days of
receiving it stating how the programme does not comply; otherwise, the
Contractor is to proceed in accordance with the programme.
As we mentioned in Section 1.7, the Contractor is required to give advance
notice or early warning to the Engineer or Employer of potential events which
might adversely affect or delay the works. There is no similar obligation on the
Engineer or Employer.
Linked to the requirement to maintain valid programmes and to advise the
Engineer or Employer of potential delaying events is the requirement to sub-
mit monthly progress reports (Section 4.4).
Each report must include charts and detailed descriptions of progress,
photographs, details of the manufacture of each major item of plant and
materials, records of the Contractor ’ s personnel, copies of quality assurance
documents and the like, lists of notices given with respect to Employer ’ s and
Contractor ’ s claims, safety statistics and comparisons of planned and actual
progress and details of measures being, or to be, adopted to overcome delays.
As we noted in Section 1.7, if the Contractor fails to provide a progress
report as required he will not be entitled to receive an interim payment for the
relevant period.