7.2 PROGRAMME CLAUSE 8 OF THE CONTRACTS PROVIDES THAT THE COMMENCEME...
Clause 8 of the contracts provides that the commencement date for the works
must be notified to the contractor at least seven days beforehand unless otherwise
stated in the contract. After receiving the instruction the contractor must pro-
ceed without delay and must complete the whole of the works and any section
within the time for completion of the works or that section (Clauses 8.1, 8.2).
The contractor must submit to the contract engineer (or, in the case of the
Silver Book, the employer or his representative) a programme within 28 days
after receiving the instruction to commence.
The programme is important in any construction project for at least these
two reasons:
●
it is the basis for monitoring the contractor ’ s progress and planning project
activities; and
●
it becomes a base reference for the relevant decision-maker (engineer or
employer) to determine the contractor ’ s claims for extensions of time for
completion arising from delaying events.
Broadly speaking, in FIDIC contracts the programme has to show:
●
the order of execution of the works, including the anticipated timing of
each major stage of the works;
●
the sequencing of the works;
●
the periods for review of contractor ’ s documents;
●
the sequence and timing of inspections and tests.
Whatever the specific contract, generally the programme should show that
the works will be completed within the time for completion and should identify
the critical path. In the FIDIC contracts, the programme should also be accom-
panied by a supporting report (or method statement) setting out how the
contractor intends to execute the works and the resources he intends to use.
This is a matter of good practice which should probably apply whatever the
contract.
An important feature of FIDIC contracts is that the contractor is required
to give advance notice or early warning to the engineer or employer of
potential events which might adversely affect or delay the works. This require-
ment has a far wider application than just in relation to the programme. The
purpose is to enable the contractor and engineer or employer to work together
to minimise the effects of the potential delaying event. The notice gives the
engineer or employer the opportunity to take action to overcome the problem
before the contractor incurs delay or additional cost.