IN MANAGING THE RISK OF THE PROJECT SCHEDULE WE ARE MANAGING THE R...

19. In managing the risk of the project schedule we are managing the riskthat the project will not be delivered or completed on time. If we as-sume that the project’s possible completion dates are normally distrib-uted and we promise the client the most likely of the project’s possiblecompletion dates, what is the probability that the project will be deliv-ered late?a. 5%b. 10%c. 50%d. 77%