34. The key inputs to activity definition are:

a. Work breakdown structure, the project schedule, and the network

diagram.

b. Project schedule, progress reports, and change requests.

... 9618$$

CH12

09-06-02 15:00:21

PS

c. The project network diagram, constraints, and durations.

d. The work breakdown structure, the scope statement, and historical

information that supports the applicable activity.