A PROJECT MANAGER WANTS TO BETTER CONTROL THE PROCEDURE FOR SANCTI...

31. A project manager wants to better control the procedure for sanctioning

work that is done on the project. He initiates a system for doing this. It

... 9618$$

CH14

09-06-02 15:00:32

PS

requires written authorization to begin work on a specific activity or a

work package. What is this system called?

a. Project charter

b. Team charter

c. Work authorization

d. Change management