5. A project manager has discovered a problem and is trying to determine
the cause. The process whereby he identifies the variables that have the
most influence on the project by holding all the variables constant and
changing one at a time is called:
a. Product correlation.
b. Design of an experiment.
c. System integration.
d. Output processing.