5. A project manager has discovered a problem and is trying to determine

the cause. The process whereby he identifies the variables that have the

most influence on the project by holding all the variables constant and

changing one at a time is called:

a. Product correlation.

b. Design of an experiment.

c. System integration.

d. Output processing.