22. A project manager is in need of a solution to a problem. He decides

that the best thing will be to arrange a meeting to solve the problem

rather than solve the problem himself or by having one of the project

team members solve it individually. Generally, this will result in:

a. The group taking more time than one individual.

b. The solution to the problem being less accurate.

c. The group taking less time than an individual.

d. It depends on the specific problem.