IN THE MONTE CARLO TECHNIQUE, WHAT IS THE CRITICALITY INDEX

15. In the Monte Carlo technique, what is the criticality index?a. The number of days the project will be late divided by the projectdurationb. The percent of time a given activity will be on the critical pathc. The percent of time an activity will be lated. The sum of the duration of the critical path activities divided by theproject expected value for duration