15. Answer: c
In the work breakdown structure the lowest level of breakdown is the work
package. This does not mean that work cannot be divided any further. Work
packages are usually broken down into tasks, and tasks can be further broken
down into activities. The point here is that the project manager is concerned
about things down to the work package level. In a relatively large project the
project manager would have subproject managers or work package managers
that would further breakdown the work in their own work breakdown struc-
tures.