QUESTIONS 12 THROUGH 15 REFER TO THE DIAGRAM IN FIGURE 2 AND THE TABLE...

17. Crashing the schedule means:

a. Making the project shorter by any economic means.

b. Running the project team on overtime.

c. Doing activities that were in sequence in parallel.

d. Getting out of town before the project is in trouble.